Big Country > recent projects / media gallery > recent projects

Recent Projects

Brooks
Company: Pengrowth
Description: Installed Pipeline & Headers
Duration: 14-Jun-11 – 08-Aug-11
Cost: $2,500,000.00

Medicine Hat
Company: Suncor
Description: Installed 239 wells P3 Phase 4
Duration: 30-Nov – 15-Aug-11
Cost: $1,500,000.00

Company: Cenovus
Description: 50KM Fibre spar
Duration: 6-Sept-11 – 30-Oct-11
Cost: $2,000,000.00

Estevan
Company: NAL Hoffer
Description: Instaled 40 km of gathering
Duration: 6-Sept-11 – 20-Jan-12
Cost: $3,000,000.00

Swift Current
Company: Talisman
Description: Installed 3, 4, 6" fiberglass
Duration: 15-May-11 – 31-Oct-11
Cost: $1,000,000.00

 

Ponoka
Company: ATCO Pipelines
Description: Installed Southern Extension
Phase 3 - 64000m 8"
Duration: 01-Jun-11 – 15-Oct-11
Cost: $10,000,000.00

Whitecourt
Company: Pengrowth
Description: Installed 1400 meters 6" fiberglass, 2100 meters 4" flexpipe, 3 site reworks, 3 camelbacks, 43 crossings, risers, tie-ins
Duration: 25-Aug-11 – 30-Sept-11
Cost: $550,000.00

Slave Lake
Company:Apache Canada
Description: Installed 6800 mts 3" 3000mts ROW
Plus Liner Pulls
Duration: 17-Jun -11 – 30-Sep-11
Cost: $1,250,000.00

Fort St John
Company: Shell Canada Ltd.
Description: Installed 3-28 to 4-17 Quad line 6",10", 12",12" Duration: 1-Sept-11 – 15-Nov-11
Cost: $1,000,000.00

Company: CNRL
Description: Installed Septimus Pipeline 16" & 6" common ditch for 22km & single 16" 11km
Duration: 11-7-11 – 1-Nov-11
Cost: $10,000,000.00


 